Reported AI capex shortfall tied to delayed third-party data centers
Benzinga·
Last close$530.61
Day change
Market cap$3.94T
P/E27.75
P/B8.38
Earnings yield3.60%
FCF yield1.52%
Dividend yield0.68%
Close, Nov 6, 2026
Microsoft spent about $5 billion less than expected on AI infrastructure in the September quarter, which the CFO attributed to delays at outside cloud providers without naming them. A research firm's satellite review reportedly links the gap to construction and permitting delays at projects tied to IREN in Texas and Nebius in New Jersey, and Microsoft separately dropped a planned U.K. site with Nscale over grid access. Quarterly capital spending of $45.2 billion came in below the roughly $50.7 billion analysts had expected. The reporting raises the question of whether the timing shift is temporary or whether capacity from partners will arrive later than planned.
- Microsoft posted quarterly capital spending of $45.2 billion versus about $50.7 billion expected.
- CFO Amy Hood attributed the roughly $5 billion shortfall to delays involving outside cloud providers, without naming them.
- Research firm Aterio reportedly tied the gap to IREN-linked projects in Texas, including a Horizon 4 facility that lacked backup generators and cooling equipment in an October 21 satellite review.
- A New Jersey project developed by DataOne for Nebius reportedly could see about 140 megawatts move into 2027 after permit and fuel-cell approval delays.
- Microsoft scrapped a planned 50-megawatt U.K. data center deal with Nscale in October due to power supply uncertainty and grid access delays into the 2030s, per Benzinga.
- The IREN and Nebius contracts were reported at $9.7 billion and $17.4 billion respectively.